Short answer: no. In Anakainisi Katoikias 2026 (Anakainizo 2026), the first ΠΕΑ (Energy Performance Certificate) and the ΗΤΚ (Electronic Building Identity) are not submitted with the application. They are filed within 3 months of the application being found eligible. Miss that deadline and the application is rejected automatically. Both remain mandatory; only the timing changes.
The myth: "no ΠΕΑ, no application"
You often read that you first get the ΠΕΑ and the ΗΤΚ and only then apply. The confusion is understandable. The first ΠΕΑ is indeed mandatory and decides whether the home gets into the programme: it must show energy class Γ or lower (Γ–Η). The official documents, however, place it after the application, not inside it.
Two parts of the Implementation Guide (October 2026) say so plainly:
- Annex I-A: the application documents. The list has five items: (1) the building permit or another document proving legality, including the filing to legalise any unauthorised construction; (2) a certificate from the municipality, if the address in the documents differs from the current one; (3) the disability certification notice, for a disability of at least 67%; (4) a family status certificate issued in the last month, for three dependent children; (5) the large-family certificate with a digital signature. Items (3)–(5) are needed only if you qualify for the matching bonus, and every document must be valid on the day you submit. The ΠΕΑ and the ΗΤΚ are not on the list.
- §5.1.2: the responsible declaration. With the application you declare that the first ΠΕΑ and the ΗΤΚ will be filed within 3 months, and you accept that if they are not, the application is rejected automatically.
Article 8 §5 of ΚΥΑ 86272/ΕΞ2026, as amended by ΚΥΑ 116171/ΕΞ2026 sets the same rule.
Two stages: the application first, then the ΠΕΑ and ΗΤΚ
- 1
Stage 1: the financing application
You submit the application on anakainisi.tee.gov.gr with your TAXISnet credentials. You upload the Annex I-A documents, the works plan with its amounts (renovation, energy measures, auxiliary costs) and the responsible declaration on the ΠΕΑ and ΗΤΚ. The eligibility certificate is pulled in automatically through the property ID number (ATAK).
- 2
Stage 2: within 3 months, the first ΠΕΑ and the ΗΤΚ
Once the application is found eligible, you file the first ΠΕΑ and the ΗΤΚ together, before the inclusion decision. The energy inspector also enters a proposal of energy measures, which you accept electronically.
Then come the inclusion decision, the advance and the works, with a deadline of 18 months from inclusion and 31 December 2028 at the latest. At the end the second ΠΕΑ is issued (see below).
What you upload, and when, at a glance:
| What | When |
|---|---|
| Building permit or other legality document, filing to legalise unauthorised construction | With the application |
| Works plan with amounts | With the application |
| Responsible declaration on the ΠΕΑ and ΗΤΚ | With the application |
| Documents for a bonus (disability, three children, large family) | With the application, if they apply to you |
| Eligibility certificate | Pulled in automatically |
| Title deed, tax assessment | Not uploaded: the data is pulled in automatically |
| First ΠΕΑ | Within 3 months of the application being found eligible |
| ΗΤΚ | Together with the first ΠΕΑ, in the same 3 months |
| Second ΠΕΑ | After the works, within their deadline |
The 3 months: when the clock starts and what happens if you miss it
If the first ΠΕΑ and the ΗΤΚ are not filed within the 3 months, the application is rejected automatically. You already gave your consent to that rejection in the responsible declaration that goes with the application.
When to start counting. The ΚΥΑ counts the 3 months from the moment the application is marked 'initially eligible'. In some sections the Implementation Guide counts from the 'eligible' status that follows the final ranking tables. Count from the earlier of the two and you will not fall outside the deadline.
Two more points about the ΗΤΚ:
- When you file it, you need a certificate of completeness, and the legalisation of any unauthorised construction must have reached final status.
- The platform automatically cross-checks it against the electricity supply number, the floor area, the building's age and the permit. If something does not match, the application is rejected and you have 7 days to object.
Why it pays to start early
You do not have to wait for the eligibility decision to get moving:
- The cost already counts. The first ΠΕΑ and the ΗΤΚ are the only costs that are eligible before the inclusion decision: from 2 June 2026. Every other cost counts from the date of inclusion.
- The Guide expects it. §9 of the Implementation Guide places the first energy inspection in the stage of preparing and submitting the application.
- You know where you stand. If the first ΠΕΑ shows class Β or better, the home is not eligible. Better to know before you plan any works.
One thing, however, must happen before the application: if there is unauthorised construction, the legalisation must be filed. By the time you file the ΗΤΚ it must be final, and by the final payment it must be complete. The full preparation list is in the preparation guide.
Who applies: you, with or without a technical consultant
You, the beneficiary, submit the application yourself with your TAXISnet credentials. If you want, you submit it together with a technical consultant, who is optional:
- The consultant is an engineer, as an individual, registered with the Technical Chamber of Greece (TEE).
- You appoint them in the system by their tax number (AFM) and authorise them through the Annex II declaration (item 11).
- You cannot be the technical consultant on your own application, even if you are an engineer.
- Either you or the consultant enters the renovation proposal (Annex V). No physical signature is needed: the electronic submission counts as a joint signature.
For the first ΠΕΑ you will still need an energy inspector, and you choose them yourself from the register of energy inspectors.
The second ΠΕΑ: a different inspector, drawn by the TEE
After the works are finished, you or the technical consultant enter the invoices and request a draw. The TEE then assigns a different energy inspector from the one who issued the first ΠΕΑ, plus a building inspector. The second ΠΕΑ is issued and filed within the works deadline.
The second ΠΕΑ must show an improvement of at least one energy class over the first (for example, from Γ to Β).
ΠΕΑ, ΗΤΚ and other auxiliary costs: 100%, but at the end
Auxiliary costs are covered 100%, on top of the subsidy, and up to 2,500 € including VAT in total per application. Each cost also has its own limit:
| Cost | Maximum covered |
|---|---|
| First ΠΕΑ | 75 € + 2.90 €/m², up to 465 € |
| Second ΠΕΑ | 75 € + 2.90 €/m², up to 465 € |
| ΗΤΚ | 175 € + 3.50 €/m², up to 645 € |
| Technical consultant (if you appoint one) | 285 € + 1.75 €/m², up to 520 € |
| Building inspector | 290 € per visit |
| Permits and studies | up to 200 € each, up to 400 € in total |
What matters is when they are paid: only after the completion declaration has been checked successfully, from the second instalment. What you have already paid yourself (energy inspector, ΗΤΚ) is reimbursed to you. The technical consultant is paid once the works are complete and the energy target is met.
The 60% advance and the 40% of your own share
After the inclusion decision, 60% of the approved subsidy is credited to a dedicated account in your name. You cannot use it straight away, though:
- First you pay the contractors you chose, by bank transfer, 40% of your own share, and upload the proof.
- The early auxiliary costs count towards that 40%: the first ΠΕΑ and the ΗΤΚ.
- After that, the whole advance is channelled to the contractors through the system.
Example: if your own share is 10,000 €, 40% of it is 4,000 €. If you have already paid, say, 800 € for the ΠΕΑ and ΗΤΚ, you have 3,200 € left to pay the contractors before the advance can be used. To see your own share for your property, use our calculator.
When and where to apply
- Closed (vacant) homes: from 29 October 2026 to 11 January 2027, on anakainisi.tee.gov.gr, with TAXISnet credentials and a valid eligibility certificate.
- Open (occupied) homes: a new call will be published.
- Order: the exact submission time counts, until the budget runs out, with separate ranking tables per region. Applications that do not fit go on a reserve list. Within the window you can withdraw your application and submit it again.
Since the ΠΕΑ and ΗΤΚ are not part of the application, they do not hold back your place in the queue. Just do not let the 3 months run out. All the dates are in deadlines & key dates, and the full picture of the programme is in the Anakainisi Katoikias guide.
Want help with the ΠΕΑ and the ΗΤΚ?
Tell us what you need for the first ΠΕΑ and the ΗΤΚ, which are filed within the 3 months. Your request goes to partner engineers in your area.
A whole number, from 10 to 1000.
Or first calculate your subsidy
Do I need a ΠΕΑ to apply for Anakainisi Katoikias?
Not for the application itself. The first ΠΕΑ is not among the application documents (Annex I-A of the Implementation Guide). With the application you sign a responsible declaration that you will file it, together with the Electronic Building Identity (ΗΤΚ), within 3 months of the application being found eligible. The ΠΕΑ is still mandatory; only the timing changes.
What happens if I do not file the ΠΕΑ and ΗΤΚ within the 3 months?
The application is rejected automatically. In the responsible declaration that goes with the application you expressly accept this rejection. To be safe, count the 3 months from the moment the application is marked 'initially eligible': that is where the ΚΥΑ starts the clock.
Can I apply on my own, without an engineer?
Yes. You submit the application yourself, with your TAXISnet credentials, on anakainisi.tee.gov.gr. If you want, you can appoint a technical consultant: an engineer, as an individual, registered with the Technical Chamber of Greece (TEE). It is optional. For the first ΠΕΑ you will still need an energy inspector, whom you choose yourself from the register of energy inspectors.
Can I get the ΠΕΑ and ΗΤΚ before applying?
Yes. Their cost counts as eligible from 2 June 2026, and the Implementation Guide places the first energy inspection in the stage of preparing and submitting the application. With an early ΠΕΑ you know in advance whether the home is in class Γ–Η. What you cannot do is file the ΠΕΑ and ΗΤΚ after the 3 months.
Who pays for the ΠΕΑ and the ΗΤΚ?
The programme covers them 100%, within the 2,500 € limit for all auxiliary costs and on top of the subsidy. It pays them at the end, though: from the second instalment, once the completion declaration has been checked. If you paid them yourself, you are reimbursed. And what you paid for the first ΠΕΑ and the ΗΤΚ counts towards the 40% of your own share that you need to pay before the advance can be used.